Easy-to-use Project Management Software. What is Critical Path

 

Easy-to-use Project Management Software program to track multiple projects. It combines high-level cross-project overview capability with detailed critical path project management of schedule, staffing, and expenditures. PERT and Gantt Chart capabilities, task outline numbering, and more. A comprehensive multi-shift work-calendar defines working and non-working days, and holidays. A large number of customizable reports and charts are available. Text and graphics file output capabilities are compatible with Word Processors, Spreadsheets, and Email.

Minute Man Plus $99.95 Secure Payment Options

Limited Time Offer! Buy & Keep MinuteManPlus From This Site to Get a Free Copy of:
Complete Excel Training Course AND OzGrid Add-ins Collection . Send payment confirmation to [email protected] 31 Days After Purchase. $139.90 Extra for Free

Risk Free 30-day money-back guaranteeMinute Man   $49.95 Secure Payment OptionsBack to: Minute Man Plus Project Management Software Or Minute Man

 What is Critical Path

The Critical Path represents the sequence of tasks or events that directly effect the completion of a project. Knowing the Critical Path allows the project manager to shorten or at least control a project's schedule by focusing on those tasks which directly affect the project's completion. This is called Critical Path Management.

In the simple example at left, Tasks 2 and 3 both Start when Task 1 is complete, and Task 4 Start s when tasks 2 and 3 are both complete. Since Task 2 takes 5 days, and Task 3 tasks only one day, it is obvious that Task 2 drives the Start of Task 4, and thus the completion of the project.

The Critical Path in this example is the sequence of tasks 1, 2, and 4. If any one of those lengthens (or shortens) by a day, the project's completion will change by that amount. 

Up to a point Task 3's duration does not affect the project completion; Task 3 is said to be 'Off the Critical Path". However, if Task 3 were to change to 6 days duration, it would now dictate the Start of Task 4; Task 3 would be On the Critical Path, and Task 2 would be Off.

It is common practice to identify the Critical Path in RED to make it stand out, as shown in the diagram.

The way to shorten a project's schedule is to focus on shortening the duration of the tasks on the critical path (i.e. paying more for expedited delivery of a crucial component.) 

NOTE: You can't make the Critical Path go away. - No matter how hard you work to shorten your projects schedule, there will still always be some critical path. Shortening some tasks just moves the critical path over to other tasks that haven't been optimized yet

Back to: Minute Man Plus Project Management Software Or Minute Man

Special! Free Choice of Complete Excel Training Course OR Excel Add-ins Collection on all purchases totaling over $70.00. ALLpurchases totaling over $150.00 gets you BOTH! Purchases MUST be made via this site. Send payment proof to [email protected] 31 days after purchase date.



Instant Download and Money Back Guarantee on Most Software

EXCEL VIDEO TUTORIALS

Excel Trader PackageTechnical Analysis in Excel With $139.00 of FREE software!

Microsoft � and Microsoft Excel � are registered trademarks of Microsoft Corporation. OzGrid is in no way associated with Microsoft